by Carl Backhouse | Jul 3, 2018 | Case Studies, Design, Heating & Cooling, Lighting, M&E, Ventilation
Bombardier Transport V-Shop June 2014 - June 2016 £3.32 Million Balfour Beatty Key Project Features: 33kV, 25kV & 6.6kV HV substation/ switchgear & distribution HV/LV transformed power supplies Operational interlock system 25kV overhead lines (OLE) High...
by Carl Backhouse | Jun 28, 2018 | Case Studies, M&E, Stations
Euston Station Remodel Sept 2014 - May 2016 £2.385 Million Balfour Beatty Key Project Features Existing M&E Surveys Relocation of Existing Services LV Distribution & Containment Lighting incl. Standby & Emergency General Power & Data Above...
by Carl Backhouse | Jun 28, 2018 | Case Studies, Stations
Northampton Castle Station Redevelopment March 2013 - October 2015 £1.998 Million Buckingham Group Key Project Features HV/LV transformed power supply Isolated Earthing & Bonding systems to new NWR standards HVAC Services Systems BMS Control Systems Electrical...
by Carl Backhouse | Jun 27, 2018 | Case Studies, Stations
Wakefield Westgate Station Redevelopment Sept 2012 - May 2014 £1.520,000 Buckingham Group Contracting Key Project Features HV/LV transformed power supply Isolated Earthing & Bonding systems to new NWR standards HVAC Services Systems BMS Control Systems...
by Carl Backhouse | Jun 27, 2018 | Case Studies, CET, Fuel, Maintenance, Rail Depot Systems
Fuelling Facility – Croft Street, Preston Depot April 2016 - December 2016 £280,000 Buckingham Group / Network Rail Key Project Features Fuel, Oil and Coolant System Power Points Electrical Services Distribution Systems External Lighting Systems Lighting...