Howdon Satellite Depot
Completed
Value
Circa £70m
Project
Additional Depot Facility
Client
(Contracting for Nexus)
Emeg were responsible for undertaking the detailed design, installation and coordination of the mechanical and electrical installations required to create a suitable environment within the depot sidings, workshop and office facilities.
Key Project Features
- Preferred M&E service provider
- Dedicated on-site project management
- Innovative bespoke solutions
- Delivered on time & on budget
- Health & Safety top priority
- No on-site accidents.
Project Background
Buckingham Group Contracting Ltd (BGCL) were appointed by Nexus as the design and build contractor for the complete scheme and contracted Emeg as their preferred railway M&E engineering services provider.
Emeg were responsible for undertaking the detailed design, installation and coordination of the mechanical & electrical services installations required to create a suitable environment within the depot sidings, the workshop and office facilities within the accommodation building.
- safeNet Depot Protection System (DPS)
- Points heating
- Automatic derailer
- Mechanical & electrical services
- LV distribution & earthing
- Lighting, telecoms & fire protection
- Gas & water supply
- Ventilation & drainage
- Heating & cooling